project-risk-register
Identifies, assesses, and prioritizes project risks using probability-times-impact scoring (risk matrix), then assigns owners, mitigation plans, contingencies, and triggers to track risk evolution over the project lifecycle. Use when managing project uncertainty, building a risk register, conducting risk assessments, defining risk mitigation plans, or when user mentions risk register, risk management, probability-impact matrix, or asks "what could go wrong with this project?".
- Installs
- 103
- Last 24h
- —
- Trending rank
- —
- Security
- Not audited
Install
Works with every agent the skills CLI supports.
npx skills add https://github.com/lyndonkl/claude --skill project-risk-register- 01
Install
Run the command in your project. The CLI asks which agents to install for.
- 02
Describe the task
Ask your agent for something this skill covers. It loads project-risk-register automatically when relevant.
- 03
Review the result
The agent follows the SKILL.md steps, scripts and references bundled with the skill.
SKILL.md
The instructions your agent reads when the skill is triggered.
Project Risk Register
Table of Contents
Risk Matrix (5×5 Probability×Impact):
Impact → 1 2 3 4 5
Prob ↓ Minimal Minor Moderate Major Severe
5 High │ Medium │ Medium │ High │ High │ Critical│
│ 5 │ 10 │ 15 │ 20 │ 25 │
4 │ Low │ Medium │ Medium │ High │ High │
│ 4 │ 8 │ 12 │ 16 │ 20 │
3 Medium │ Low │ Low │ Medium │ Medium │ High │
│ 3 │ 6 │ 9 │ 12 │ 15 │
2 │ Low │ Low │ Low │ Medium │ Medium │
│ 2 │ 4 │ 6 │ 8 │ 10 │
1 Low │ Low │ Low │ Low │ Low │ Medium │
│ 1 │ 2 │ 3 │ 4 │ 5 │
Risk Thresholds:
- Critical (≥20): Escalate to exec, immediate mitigation required
- High (12-19): Active management, weekly review, documented mitigation
- Medium (6-11): Monitor closely, monthly review, contingency plan
- Low (1-5): Accept or minimal mitigation, quarterly review
Example: Software Migration Project
| Risk ID | Risk | Prob | Impact | Score | Owner | Mitigation | Contingency |
|---|---|---|---|---|---|---|---|
| R-001 | Third-party API deprecated mid-project | 3 | 4 | 12 (Medium) | Eng Lead | Contact vendor for deprecation timeline | Build abstraction layer for quick swap |
| R-002 | Key engineer leaves during critical phase | 2 | 5 | 10 (Medium) | EM | Knowledge sharing, pair programming | Contract backup engineer |
| R-003 | Data migration takes 3× longer than estimated | 4 | 4 | 16 (High) | Data Lead | Pilot migration on 10% data first | Extend timeline, reduce scope |
Workflow
Copy this checklist and track your progress:
Risk Register Progress:
- [ ] Step 1: Identify risks across categories
- [ ] Step 2: Assess probability and impact
- [ ] Step 3: Calculate risk scores and prioritize
- [ ] Step 4: Assign owners and define responses
- [ ] Step 5: Monitor and update regularly
Step 1: Identify risks across categories
Brainstorm what could go wrong using structured categories (technical, schedule, resource, external, scope). See Common Patterns for category checklists. Use resources/template.md for register structure.
Step 2: Assess probability and impact
Score each risk on probability (1-5: rare to almost certain) and impact (1-5: minimal to severe). Involve subject matter experts for accuracy. See Risk Scoring Framework for definitions.
Step 3: Calculate risk scores and prioritize
Multiply Probability × Impact for each risk. Plot on risk matrix (5×5 grid) to visualize risk profile. Focus mitigation on Critical/High risks first. See resources/methodology.md for advanced techniques like Monte Carlo simulation.
Step 4: Assign owners and define responses
For each High/Critical risk, assign named owner (not "team"), define mitigation (reduce probability), contingency (reduce impact), and triggers (when to activate contingency). See resources/template.md for response planning structure.
Step 5: Monitor and update regularly
Review risk register weekly (active projects) or monthly (longer projects). Update probabilities/impacts as context changes, add new risks, retire closed risks, track mitigation progress. See Guardrails for monitoring cadence.
Common Patterns
Risk categories (use for brainstorming):
- Technical risks: Technology failure, integration issues, performance problems, security vulnerabilities, technical debt, complexity underestimated
- Schedule risks: Dependencies delayed, estimation errors, scope creep, resource unavailability, critical path blocked
- Resource risks: Key person leaves, skill gaps, budget overrun, vendor/contractor issues, equipment unavailable
- External risks: Regulatory changes, market shifts, competitor actions, economic downturn, natural disasters, vendor bankruptcy
- Scope risks: Unclear requirements, changing priorities, stakeholder disagreement, gold-plating, mission creep
- Organizational risks: Lack of executive support, competing priorities, insufficient funding, organizational change, political conflicts
By project type:
- Software projects: Third-party API changes, dependency vulnerabilities, cloud provider outages, data migration issues, browser compatibility, scaling problems, security breaches
- Construction projects: Weather delays, material shortages, permit issues, labor strikes, soil conditions, cost overruns, safety incidents
- Product launches: Manufacturing delays, supply chain disruption, competitor launch, pricing miscalculation, market demand lower than expected, quality issues
- Organizational change: Employee resistance, communication breakdown, training inadequate, budget cuts, leadership turnover, cultural misalignment
By risk response type:
- Mitigate (reduce probability): Training, prototyping, process improvements, redundancy, quality checks, early testing
- Contingency (reduce impact if occurs): Backup plans, insurance, reserves (time/budget), alternative suppliers, rollback procedures
- Accept (do nothing): Low-score risks not worth mitigation cost, residual risks after mitigation
- Transfer (shift to others): Insurance, outsourcing, contracts (penalty clauses), warranties
Typical risk profile evolution:
- Project start: Many medium risks (uncertainty high), few critical (pre-mitigation)
- Mid-project: Critical risks mitigated to medium/low, new risks emerge (dependencies, integration)
- Near completion: Low risks dominate (most issues resolved), few high (last-minute surprises)
- Red flag: Risk score increasing over time (mitigation not working, new issues emerging faster than resolution)
Risk Scoring Framework
Probability Scale (1-5):
- 5 - Almost Certain (>80%): Expected to occur, historical data confirms, no mitigation in place
- 4 - Likely (60-80%): Probably will occur, similar projects had this issue, weak mitigation
- 3 - Possible (40-60%): May or may not occur, depends on circumstances, some mitigation in place
- 2 - Unlikely (20-40%): Probably won't occur, mitigation in place, low historical precedent
- 1 - Rare (<20%): Very unlikely, strong mitigation, no historical precedent
Impact Scale (1-5) - adjust dimensions for project context:
For Schedule Impact:
- 5 - Severe: >20% delay (e.g., 3-month project delayed 3+ weeks), miss critical deadline, cascading delays
- 4 - Major: 10-20% delay, miss milestone, affects dependent projects
- 3 - Moderate: 5-10% delay, timeline buffer consumed, no external impact
- 2 - Minor: <5% delay, absorbed within sprint/phase, minor schedule pressure
- 1 - Minimal: <1% delay or no delay, negligible schedule impact
For Budget Impact:
- 5 - Severe: >20% budget overrun, requires new funding approval, project viability threatened
- 4 - Major: 10-20% overrun, contingency exhausted, scope cuts required
- 3 - Moderate: 5-10% overrun, contingency partially used, no scope cuts
- 2 - Minor: <5% overrun, absorbed within budget flexibility
- 1 - Minimal: <1% overrun or no budget impact
For Scope/Quality Impact:
- 5 - Severe: Core functionality lost, customer-facing quality issue, regulatory violation
- 4 - Major: Important feature cut, significant quality degradation, customer complaints
- 3 - Moderate: Nice-to-have feature cut, minor quality issue, internal workarounds needed
- 2 - Minor: Edge case feature cut, cosmetic quality issue
- 1 - Minimal: No scope or quality impact
Composite Impact (when multiple dimensions affected):
- Use maximum of any single dimension (pessimistic, conservative)
- OR use weighted average: Schedule 40%, Budget 30%, Scope/Quality 30%
Example Scoring:
Risk: "Key engineer leaves mid-project"
- Probability: 2 (Unlikely - 20% based on tenure, satisfaction, retention rate)
- Impact Schedule: 4 (Major - 3-week delay to onboard replacement, knowledge transfer)
- Impact Budget: 2 (Minor - recruiter fees, some overtime)
- Impact Scope: 3 (Moderate - may cut advanced features)
- Composite Impact: 4 (take maximum: schedule impact is worst)
- Risk Score: 2 × 4 = 8 (Medium)
Guardrails
Ensure quality:
-
Identify risks proactively, not reactively: Run risk workshops before problems occur
- ✓ Brainstorm risks at project kickoff, use checklists (technical, schedule, resource, etc.)
- ❌ Add risks only after incidents occur (reactive)
-
Be specific, not vague: "Integration fails" is vague, "Vendor API rate limits block migration" is specific
- ✓ "Third-party payment gateway rejects 10% of transactions due to fraud rules"
- ❌ "Payment issues"
-
Separate probability and impact: Don't conflate "bad if it happens" with "likely to happen"
- ✓ Asteroid hits office: Prob=1 (rare), Impact=5 (severe), Score=5 (low priority)
- ❌ Conflating: "This is really bad so it must be high priority" (ignoring low probability)
-
Assign named owners, not teams: "Engineering team" is not accountable, "Sarah (Tech Lead)" is
- ✓ Owner: Sarah (Tech Lead), responsible for monitoring and activating contingency
- ❌ Owner: Engineering Team (diffused responsibility)
-
Define mitigation AND contingency: Mitigation reduces probability, contingency handles if it occurs anyway
- ✓ Mitigation: Prototype integration early (reduce prob). Contingency: Build abstraction layer for quick swap (reduce impact)
- ❌ Only mitigation, no backup plan
-
Update regularly: Stale risk register is worse than none (false confidence)
- ✓ Weekly review for active projects (High/Critical risks), monthly for longer projects
- ❌ Create register at kickoff, never update (probabilities/impacts change as project progresses)
-
Retire closed risks: Don't let register grow indefinitely, archive mitigated/irrelevant risks
- ✓ Mark risk "Closed" with resolution date, move to archive section
- ❌ Keep all risks forever (signal-to-noise ratio degrades)
-
Escalate critical risks immediately: Don't wait for weekly meeting if Critical risk emerges
- ✓ Prob=5 Impact=5 Score=25 → Escalate to exec same day, emergency mitigation
- ❌ Wait for scheduled review (risk could materialize)
Quick Reference
Resources:
- Quick start: resources/template.md - Risk register template with scoring table, response planning, monitoring log
- Advanced techniques: resources/methodology.md - Monte Carlo simulation, decision trees, sensitivity analysis, risk aggregation, earned value management
- Quality check: resources/evaluators/rubric_project_risk_register.json - Evaluation criteria
Success criteria:
- ✓ Identified 15-30 risks across all categories (technical, schedule, resource, external, scope, org)
- ✓ All High/Critical risks (score ≥12) have named owners, mitigation plans, and contingencies
- ✓ Risk scores differentiated (not all scored 6-9; use full 1-25 range)
- ✓ Mitigation and contingency plans are specific and actionable (not "monitor closely")
- ✓ Triggers defined for when to activate contingencies (quantifiable thresholds)
- ✓ Register updated regularly (weekly for active projects, monthly for longer projects)
- ✓ Risk profile matches project phase (high uncertainty at start, decreasing over time)
Common mistakes:
- ❌ Too few risks identified (<10) → incomplete risk picture, false confidence
- ❌ All risks scored medium (6-9) → not differentiated, unclear prioritization
- ❌ Vague risks ("things might not work") → not actionable
- ❌ No risk owners assigned → diffused accountability, mitigation doesn't happen
- ❌ Mitigation without contingency → no backup plan if mitigation fails
- ❌ Created once, never updated → stale data, risks evolve
- ❌ Only negative risks (threats) → missing opportunities (positive risks)
- ❌ Risk register separate from project plan → not integrated into workflow
When to use alternatives:
- Pre-mortem: When project hasn't started, want to imagine failure scenarios (complements risk register)
- FMEA (Failure Mode Effects Analysis): Manufacturing/engineering projects needing detailed failure analysis
- Monte Carlo simulation: When need probabilistic timeline/budget forecasting (use methodology.md)
- Decision tree: When risks involve sequential decisions with branch points
- Scenario planning: When risks are strategic/long-term (market shifts, competitor actions)
FAQ
What does the project-risk-register skill do?
Identifies, assesses, and prioritizes project risks using probability-times-impact scoring (risk matrix), then assigns owners, mitigation plans, contingencies, and triggers to track risk evolution over the project lifecycle. Use when managing project uncertainty, building a risk register, conducting risk assessments, defining risk mitigation plans, or when user mentions risk register, risk management, probability-impact matrix, or asks "what could go wrong with this project?".
How do I install project-risk-register?
Run npx skills add https://github.com/lyndonkl/claude --skill project-risk-register in your project. The skills CLI detects the agents you use and copies the skill into the right folder. For Claude Code you can also place the skill folder at ~/.claude/skills/project-risk-register/ (personal) or .claude/skills/project-risk-register/ (project).
Which AI agents can use project-risk-register?
Any agent that supports the open Agent Skills format (a folder with a SKILL.md file), including Claude Code, Codex, Cursor, GitHub Copilot, Gemini CLI, Windsurf, Cline, OpenCode and more.
Is project-risk-register safe to install?
No partner security audit is available yet. Skills can run commands and scripts, so read the SKILL.md and any bundled files before installing.
Who maintains project-risk-register?
It is published by lyndonkl in lyndonkl/claude. It has 103 recorded installs.
More from lyndonkl/claude
evaluation-rubrics
lyndonkl/claude
Designs structured scoring tools with explicit criteria, performance scales, and descriptors for consistent, transparent quality assessment. Use when need quality criteria and scoring scales to evaluate work consistently, compare alternatives objectively, set acceptance thresholds, reduce subjective bias, or when user mentions rubric, scoring criteria, quality standards, evaluation framework, inter-rater reliability, or grading/assessing work.
strategy-and-competitive-analysis
lyndonkl/claude
Develops business strategies grounded in rigorous competitive and market analysis using proven frameworks (Good Strategy kernel, Porter's 5 Forces, SWOT, Blue Ocean, Playing to Win, Value Chain Analysis, BCG Matrix). Use when developing strategy (market entry, product launch, expansion, M&A, turnaround), conducting competitive analysis, making strategic decisions (build vs buy, pricing, positioning), planning strategic initiatives, or when user mentions strategy, competitive analysis, Porter's 5 Forces, SWOT, market positioning, or strategic frameworks.
scientific-manuscript-review
lyndonkl/claude
Guides systematic multi-pass review and editing of scientific manuscripts (research articles, reviews, perspectives) to improve clarity, structure, scientific rigor, and reader comprehension. Use when reviewing or editing research manuscripts, journal articles, or perspectives, when user mentions manuscript, paper draft, article, research writing, journal submission, reviewer feedback, or needs to improve scientific writing.
memory-retrieval-learning
lyndonkl/claude
Creates evidence-based learning plans that maximize long-term retention through spaced repetition, retrieval practice, interleaving, and elaboration. Guides through goal definition, material breakdown, review scheduling, and progress tracking. Use when long-term knowledge retention is needed, studying for exams or certifications, learning new job skills or technology, mastering substantial material, combating forgetting, or when user mentions studying, memorizing, learning plans, spaced repetition, flashcards, active recall, or durable learning.
socratic-teaching-scaffolds
lyndonkl/claude
Guides learners to discover knowledge through strategic Socratic questioning and progressive scaffolding removal. Combines question ladders, misconception detectors, Feynman explanations, and worked-example fading to build durable understanding. Use when teaching complex concepts, correcting misconceptions, onboarding team members, mentoring problem-solving, or designing self-paced learning. Use when user mentions "teach me", "help me understand", "explain like I'm", "learning path", "guided discovery", or "Socratic method".
grant-proposal-assistant
lyndonkl/claude
Guides creation and review of competitive grant proposals (NIH R01/R21/K, NSF, foundations) by applying reviewer-perspective thinking to ensure clear hypotheses, compelling significance, genuine innovation, and feasible approaches. Use when writing or reviewing grant proposals, crafting specific aims, drafting significance/innovation/approach sections, or when user mentions R01, R21, K-series, grant writing, proposal review, study section, or fundable hypothesis.
Popular other skills
hyperframes-cli
heygen-com/hyperframes
The HyperFrames CLI by job - scaffold, check, look at frames, edit the timeline, preview, render locally or in the cloud, publish, project history - plus reading its JSON and recovering from build or render failures.
triage
mattpocock/skills
Move issues and external PRs through a state machine of triage roles, categorise, verify, grill if needed, and write agent-ready briefs.
ask-matt
mattpocock/skills
Ask which skill or flow fits your situation. A router over the skills in this repo.
to-questionnaire
mattpocock/skills
Turn a decision you can't fully answer into a questionnaire for someone else to fill in.
loop-me
mattpocock/skills
Grill me about specs for the workflows I want to build, within this workspace.