critical-path-analyzer

Analyze project critical path from schedule data. Identify critical activities, calculate float, and assess schedule risk.

Installs
124
Last 24h
—
Trending rank
—
Security
Not audited

Install

Works with every agent the skills CLI supports.

npx skills add https://github.com/datadrivenconstruction/ddc_skills_for_ai_agents_in_construction --skill critical-path-analyzer
  1. 01

    Install

    Run the command in your project. The CLI asks which agents to install for.

  2. 02

    Describe the task

    Ask your agent for something this skill covers. It loads critical-path-analyzer automatically when relevant.

  3. 03

    Review the result

    The agent follows the SKILL.md steps, scripts and references bundled with the skill.

SKILL.md

The instructions your agent reads when the skill is triggered.

Critical Path Analyzer

Business Case

Problem Statement

Schedule management requires understanding:

  • Which activities are critical?
  • How much float exists?
  • What delays impact completion?
  • Where to focus resources?

Solution

Analyze schedule network to identify critical path, calculate float, and provide actionable schedule insights.

Technical Implementation

import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Set
from dataclasses import dataclass, field
from datetime import date, timedelta
from enum import Enum
from collections import defaultdict


class ActivityStatus(Enum):
    NOT_STARTED = "not_started"
    IN_PROGRESS = "in_progress"
    COMPLETED = "completed"
    DELAYED = "delayed"


@dataclass
class Activity:
    activity_id: str
    name: str
    duration: int  # days
    predecessors: List[str]
    early_start: int = 0
    early_finish: int = 0
    late_start: int = 0
    late_finish: int = 0
    total_float: int = 0
    free_float: int = 0
    is_critical: bool = False
    status: ActivityStatus = ActivityStatus.NOT_STARTED
    percent_complete: float = 0
    actual_start: Optional[date] = None
    actual_finish: Optional[date] = None


@dataclass
class CriticalPathResult:
    critical_path: List[str]
    project_duration: int
    activities: Dict[str, Activity]
    near_critical: List[str]  # Float < 5 days
    total_float_days: int


class CriticalPathAnalyzer:
    """Analyze project critical path."""

    NEAR_CRITICAL_THRESHOLD = 5  # days

    def __init__(self, project_start: date):
        self.project_start = project_start
        self.activities: Dict[str, Activity] = {}

    def add_activity(self,
                     activity_id: str,
                     name: str,
                     duration: int,
                     predecessors: List[str] = None):
        """Add activity to network."""

        self.activities[activity_id] = Activity(
            activity_id=activity_id,
            name=name,
            duration=duration,
            predecessors=predecessors or []
        )

    def import_from_dataframe(self, df: pd.DataFrame):
        """Import activities from DataFrame."""
        for _, row in df.iterrows():
            preds = row.get('predecessors', '')
            if pd.isna(preds):
                pred_list = []
            else:
                pred_list = [p.strip() for p in str(preds).split(',') if p.strip()]

            self.add_activity(
                activity_id=str(row['activity_id']),
                name=row['name'],
                duration=int(row['duration']),
                predecessors=pred_list
            )

    def _forward_pass(self):
        """Calculate early start and early finish (forward pass)."""

        # Topological sort
        sorted_activities = self._topological_sort()

        for activity_id in sorted_activities:
            activity = self.activities[activity_id]

            # Early start = max(early finish of all predecessors)
            if not activity.predecessors:
                activity.early_start = 0
            else:
                activity.early_start = max(
                    self.activities[pred].early_finish
                    for pred in activity.predecessors
                    if pred in self.activities
                )

            activity.early_finish = activity.early_start + activity.duration

    def _backward_pass(self):
        """Calculate late start and late finish (backward pass)."""

        # Find project duration
        project_duration = max(a.early_finish for a in self.activities.values())

        # Build successors map
        successors = defaultdict(list)
        for activity_id, activity in self.activities.items():
            for pred in activity.predecessors:
                if pred in self.activities:
                    successors[pred].append(activity_id)

        # Reverse topological order
        sorted_activities = self._topological_sort()[::-1]

        for activity_id in sorted_activities:
            activity = self.activities[activity_id]

            # Late finish = min(late start of all successors)
            if activity_id not in successors or not successors[activity_id]:
                activity.late_finish = project_duration
            else:
                activity.late_finish = min(
                    self.activities[succ].late_start
                    for succ in successors[activity_id]
                )

            activity.late_start = activity.late_finish - activity.duration

            # Calculate floats
            activity.total_float = activity.late_start - activity.early_start
            activity.is_critical = activity.total_float == 0

    def _topological_sort(self) -> List[str]:
        """Topological sort of activities."""

        visited = set()
        result = []

        def visit(activity_id: str):
            if activity_id in visited:
                return
            visited.add(activity_id)

            activity = self.activities.get(activity_id)
            if activity:
                for pred in activity.predecessors:
                    if pred in self.activities:
                        visit(pred)
                result.append(activity_id)

        for activity_id in self.activities:
            visit(activity_id)

        return result

    def calculate_critical_path(self) -> CriticalPathResult:
        """Calculate critical path and all float values."""

        self._forward_pass()
        self._backward_pass()

        # Find critical path
        critical_activities = [
            a.activity_id for a in self.activities.values()
            if a.is_critical
        ]

        # Near-critical activities
        near_critical = [
            a.activity_id for a in self.activities.values()
            if 0 < a.total_float <= self.NEAR_CRITICAL_THRESHOLD
        ]

        project_duration = max(a.early_finish for a in self.activities.values())
        total_float = sum(a.total_float for a in self.activities.values())

        return CriticalPathResult(
            critical_path=critical_activities,
            project_duration=project_duration,
            activities=self.activities,
            near_critical=near_critical,
            total_float_days=total_float
        )

    def get_schedule_dates(self) -> pd.DataFrame:
        """Get schedule with dates."""

        data = []
        for activity in self.activities.values():
            early_start_date = self.project_start + timedelta(days=activity.early_start)
            early_finish_date = self.project_start + timedelta(days=activity.early_finish)
            late_start_date = self.project_start + timedelta(days=activity.late_start)
            late_finish_date = self.project_start + timedelta(days=activity.late_finish)

            data.append({
                'Activity ID': activity.activity_id,
                'Name': activity.name,
                'Duration': activity.duration,
                'Early Start': early_start_date,
                'Early Finish': early_finish_date,
                'Late Start': late_start_date,
                'Late Finish': late_finish_date,
                'Total Float': activity.total_float,
                'Critical': 'Yes' if activity.is_critical else 'No'
            })

        return pd.DataFrame(data)

    def analyze_delay_impact(self,
                             activity_id: str,
                             delay_days: int) -> Dict[str, Any]:
        """Analyze impact of delay on project."""

        activity = self.activities.get(activity_id)
        if not activity:
            return {}

        absorbed_by_float = min(delay_days, activity.total_float)
        project_delay = max(0, delay_days - activity.total_float)

        # Find affected activities
        affected = []
        if project_delay > 0:
            # Activities that could be affected (successors)
            for a in self.activities.values():
                if activity_id in a.predecessors:
                    affected.append(a.activity_id)

        return {
            'activity': activity_id,
            'delay_days': delay_days,
            'available_float': activity.total_float,
            'absorbed_by_float': absorbed_by_float,
            'project_delay': project_delay,
            'affected_activities': affected,
            'is_critical_delay': project_delay > 0
        }

    def suggest_acceleration(self,
                             target_reduction: int) -> List[Dict[str, Any]]:
        """Suggest activities to accelerate to meet target."""

        result = self.calculate_critical_path()
        suggestions = []

        # Focus on critical activities
        for activity_id in result.critical_path:
            activity = self.activities[activity_id]

            # Assume can reduce by 20% max
            max_reduction = int(activity.duration * 0.2)

            if max_reduction > 0:
                suggestions.append({
                    'activity': activity_id,
                    'name': activity.name,
                    'current_duration': activity.duration,
                    'max_reduction': max_reduction,
                    'reason': 'Critical path activity'
                })

        # Sort by potential impact
        return sorted(suggestions, key=lambda x: x['max_reduction'], reverse=True)

    def export_analysis(self, output_path: str) -> str:
        """Export analysis to Excel."""

        result = self.calculate_critical_path()

        with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
            # Summary
            summary_df = pd.DataFrame([{
                'Project Start': self.project_start,
                'Project Duration': result.project_duration,
                'Project Finish': self.project_start + timedelta(days=result.project_duration),
                'Critical Activities': len(result.critical_path),
                'Near-Critical Activities': len(result.near_critical),
                'Total Float (days)': result.total_float_days
            }])
            summary_df.to_excel(writer, sheet_name='Summary', index=False)

            # Schedule
            schedule_df = self.get_schedule_dates()
            schedule_df.to_excel(writer, sheet_name='Schedule', index=False)

            # Critical Path
            critical_df = pd.DataFrame([
                {
                    'Activity': a_id,
                    'Name': self.activities[a_id].name,
                    'Duration': self.activities[a_id].duration
                }
                for a_id in result.critical_path
            ])
            critical_df.to_excel(writer, sheet_name='Critical Path', index=False)

        return output_path

Quick Start

from datetime import date

# Initialize analyzer
analyzer = CriticalPathAnalyzer(project_start=date(2024, 6, 1))

# Add activities
analyzer.add_activity("A", "Site Preparation", 10, [])
analyzer.add_activity("B", "Foundation Excavation", 15, ["A"])
analyzer.add_activity("C", "Foundation Concrete", 20, ["B"])
analyzer.add_activity("D", "Structural Steel", 30, ["C"])
analyzer.add_activity("E", "MEP Rough-in", 25, ["C"])
analyzer.add_activity("F", "Exterior Walls", 20, ["D"])
analyzer.add_activity("G", "Interior Finish", 15, ["E", "F"])

# Calculate critical path
result = analyzer.calculate_critical_path()

print(f"Project Duration: {result.project_duration} days")
print(f"Critical Path: {result.critical_path}")

Common Use Cases

1. Analyze Delay Impact

impact = analyzer.analyze_delay_impact("C", delay_days=5)
print(f"Project Delay: {impact['project_delay']} days")

2. Get Schedule Dates

schedule = analyzer.get_schedule_dates()
print(schedule[['Activity ID', 'Early Start', 'Late Finish', 'Total Float']])

3. Acceleration Suggestions

suggestions = analyzer.suggest_acceleration(target_reduction=10)
for s in suggestions:
    print(f"{s['activity']}: can reduce {s['max_reduction']} days")

Resources

  • DDC Book: Chapter 4.2 - Schedule Analysis

FAQ

What does the critical-path-analyzer skill do?

Analyze project critical path from schedule data. Identify critical activities, calculate float, and assess schedule risk.

How do I install critical-path-analyzer?

Run npx skills add https://github.com/datadrivenconstruction/ddc_skills_for_ai_agents_in_construction --skill critical-path-analyzer in your project. The skills CLI detects the agents you use and copies the skill into the right folder. For Claude Code you can also place the skill folder at ~/.claude/skills/critical-path-analyzer/ (personal) or .claude/skills/critical-path-analyzer/ (project).

Which AI agents can use critical-path-analyzer?

Any agent that supports the open Agent Skills format (a folder with a SKILL.md file), including Claude Code, Codex, Cursor, GitHub Copilot, Gemini CLI, Windsurf, Cline, OpenCode and more.

Is critical-path-analyzer safe to install?

No partner security audit is available yet. Skills can run commands and scripts, so read the SKILL.md and any bundled files before installing.

Who maintains critical-path-analyzer?

It is published by datadrivenconstruction in datadrivenconstruction/ddc_skills_for_ai_agents_in_construction. It has 124 recorded installs.

More from datadrivenconstruction/ddc_skills_for_ai_agents_in_construction

View all →

warranty-tracker

datadrivenconstruction/ddc_skills_for_ai_agents_in_construction

Track and manage construction warranties. Monitor expiration dates, claims, and manufacturer documentation.

AI & Agents996 installs

cad-to-data

datadrivenconstruction/ddc_skills_for_ai_agents_in_construction

Convert CAD/BIM files to structured data. Extract element data from Revit, IFC, DWG, DGN files.

AI & Agents333 installs

dwg-to-excel

datadrivenconstruction/ddc_skills_for_ai_agents_in_construction

Convert AutoCAD DWG files (1983-2026) to Excel databases using DwgExporter CLI. Extract layers, blocks, attributes, and geometry data without Autodesk licenses.

Data & Databases309 installs

drawing-analyzer

datadrivenconstruction/ddc_skills_for_ai_agents_in_construction

Open the skill to read its SKILL.md instructions.

AI & Agents259 installs

permit-tracking-automation

datadrivenconstruction/ddc_skills_for_ai_agents_in_construction

Automate construction permit tracking and management. Monitor application status, track renewal deadlines, manage document requirements, and integrate with municipal systems.

cost-estimation-resource

datadrivenconstruction/ddc_skills_for_ai_agents_in_construction

Calculate construction costs using resource-based method. Estimate project costs from work items, physical resource norms, and current prices.

AI & Agents193 installs

Popular ai & agents skills

View category →

google-agents-cli-publish

google/agents-cli

This skill should be used when the user wants to "publish an agent", "publish my ADK agent", "register an agent with Gemini", "publish to Gemini" (formerly Gemini Enterprise), or needs guidance on the agents-cli publish gemini command. Also use when the user wants to "manage agents in Agent Registry", "list/update/delete registered agents", or "register an MCP server". Covers ADK vs A2A registration modes, programmatic and interactive usage, flag reference, auto-detection from deployment metadata, Agent Registry fleet management, and troubleshooting. Part of the agents-cli skills suite. Do NOT use for deployment (use google-agents-cli-deploy).

AI & Agents513.9K installs

google-agents-cli-eval

google/agents-cli

This skill should be used when the user wants to "run an evaluation", "evaluate my agent", "evaluate my ADK agent", "write an eval dataset", "analyze eval failures", "compare eval results", "optimize agent", or needs guidance on the Gemini platform eval methodology and the Quality Flywheel. Covers eval metrics, dataset schema, LLM-as-judge scoring, and common failure causes. Applies to any agents-cli project, whatever framework the agent is written in. Do NOT use for agent API code patterns (ADK: use google-agents-cli-adk-code), deployment (use google-agents-cli-deploy), or project scaffolding (use google-agents-cli-scaffold).

AI & Agents513.5K installs

skill-creator

anthropics/skills

Create new skills, modify and improve existing skills, and measure skill performance. Use when users want to create a skill from scratch, edit, or optimize an existing skill, run evals to test a skill, benchmark skill performance with variance analysis, or optimize a skill's description for better triggering accuracy.

OfficialAI & Agents416.4K installs

codex-pet

prime-skills/runcomfy-agent-skills

Codex Pet generator on RunComfy. Build a Codex-compatible Codex Pet spritesheet.webp + pet.json from a single reference image, drop it into ${CODEXHOME:-$HOME/.codex}/pets/ / and Codex picks it up as a custom Codex Pet next to the 8 built-ins. This skill produces the exact Codex Pet atlas Codex expects (1536x1872 PNG/WebP, 8 cols x 9 rows, 192x208 cells, 9 animation states — idle, running-right, running-left, waving, jumping, failed, waiting, running, review). Calls OpenAI GPT Image 2 edit ONCE via the local RunComfy CLI as runcomfy run openai/gpt-image-2/edit to produce a canonical Codex Pet pose, then assembles all 9 animation rows programmatically with ImageMagick micro-transforms — no Codex Pro, no $imagegen, no OPENAIAPIKEY required, only RUNCOMFYTOKEN. Triggers on "codex pet", "create codex pet", "make codex pet", "hatch codex pet", "/hatch image", "desktop pet codex", "codex pets", "spritesheet.webp", or any explicit ask to build a custom pet for OpenAI Codex.

AI & Agents402.1K installs

full-output-enforcement

leonxlnx/taste-skill

Overrides default LLM truncation behavior. Enforces complete code generation, bans placeholder patterns, and handles token-limit splits cleanly. Apply to any task requiring exhaustive, unabridged output.

AI & Agents401K installs

executing-plans

obra/superpowers

Use when executing an implementation plan in the current session as the implementer yourself — your human partner chose inline execution, or no subagent tool is available

AI & Agents245.7K installs